To monitor data completeness, go to the Bill Explorer and set the Filters:

  • Period - select a month, and the completeness report will display data from 12 months up to the selected month

  • Resource Types - you may select multiple resource types, however, they should all be in the same Resource Category (e.g. electricity and green power, but not electricity and water)

  • Assets - select at least one asset

The Bill Explorer will display the Billed Completeness and the Total Completeness:

  • Billed Completeness - Number of days with billing data, divided by the number of days in the period (for all assets listed)

  • Total Completeness - Number of days with billing or estimated data, divided by the number of days in the period (for all assets listed)

Viewing Day Coverage for Specific Assets or Meters

To view the day coverage or completeness of specific assets or meters, check the tables below: